Exhibit 2 · EVC-1.5

Governed-Elevation Vertical Stack

The project's system priority structure rendered as a representative section at governed elevations, for field confirmation.

  1. Main duct conflicts with the bath ceiling at 7'-2". The duct cannot run at this elevation without cutting into the approved ceiling plane.
  2. Bath fan coil must sit above the 7'-2" bath ceiling and below the deck above. Duct connection to be field-verified.
  3. Fire protection main runs parallel alongside the main duct through the same overhead zone.
  4. No overhead systems run above the 8'-2" living area ceiling.